Budget vs Forecast: One City Budget, Three Forecasts in a Year
Budget vs forecast, read from San Diego's 2026 reports: the budget barely moved, the forecast was redone 3 times and beat it on 3 of 4 taxes.

When people weigh a budget vs forecast, the real split is timing, and which number you let change. A budget is the plan you approve before the year starts, and you hold yourself to it. A forecast is your best current guess of where the year will end, and you redo it every time real numbers come in. Start from a free one pager template.
One‑Pager examples
Real One-Pagers made with MakeOnepagers. Open any one to edit it as your own.
Annual Budget SummaryEdit for free(opens in a new tab)
Budget Summary ReportEdit for free(opens in a new tab)
Monthly Budget ReportEdit for free(opens in a new tab)
Department Budget Variance ReportEdit for free(opens in a new tab)
Grant Budget ReportEdit for free(opens in a new tab)
Marketing Budget vs ActualEdit for free(opens in a new tab)

To see the two side by side, we read every report the City of San Diego published on its 2026 general fund. The city approved one budget. Then it put out a fresh year-end forecast in November, January and May, before the final numbers arrived in October 2026. Across the year, the budget moved by $3.7 million, or 0.17%. The forecast's bottom line swung from a $16.8 million hole to a $1.7 million surplus.
| Budget | Forecast | |
|---|---|---|
| What it answers | What we plan to earn and spend | Where we'll actually end up |
| When it's made | Once, before the year starts | Again and again during the year |
| Who signs off | A board, council or owner | Usually the finance team |
| Does it change? | Rarely, and only by a formal vote | Every time new numbers arrive |
| What you compare it to | Actual results, at the end | The budget, while there's still time to act |
San Diego's year, report by report
San Diego's fiscal year runs from July 1, 2025 to June 30, 2026. A council budget policy calls for quarterly reports to the city council, and each one says how many months of real numbers it stands on.
| Report | Months of actuals | Revenue | Spending | Bottom line |
|---|---|---|---|---|
| Adopted budget | 0 | $2,167.4M | $2,167.4M | $0 |
| Budget after changes | n/a | $2,171.1M | $2,171.1M | $0 |
| Mid-year forecast, January 2026 | 5 | $2,157.5M | $2,174.3M | $16.8M short |
| Third quarter forecast, May 2026 | 9 | $2,160.6M | $2,158.9M | $1.7M over |
| Year-end report, October 2026 | 12, unaudited | $2,164.7M | $2,169.4M | $4.7M short |
The November report isn't in the table because it didn't forecast the whole year. It used three months of numbers and projected four major taxes plus a few spending lines, such as public safety overtime. The report says detailed year-end projections for department revenue and spending "are not included in this report."
Read down the columns and you'll spot three things:
- The budget barely moved. It went from $2,167.4 million to $2,171.1 million, a change of $3.7 million.
- The forecast moved a lot. The bottom line went from $16.8 million short in January to $1.7 million over in May, a swing of $18.5 million in four months.
- The forecast didn't land on the final number either. The year closed $4.7 million short, which the October report says requires a draw from the city's General Fund Stability Reserve.
One warning if you check the final row yourself. The October report says its revenue and spending both include a large accounting entry for a transfer of assets, mostly vehicles, out of the city's solid waste fund, and the two sides "largely offset one another." So compare the bottom lines, which that entry doesn't move, before you compare the revenue and spending totals.
Hotel tax: a budget that held and a forecast that moved
One line shows the difference best. San Diego's general fund budgeted $170.3 million of hotel tax, which the city calls transient occupancy tax. That figure stayed at $170.3 million in every report of the year. The forecast moved three times.
| Report | Hotel tax, general fund | Gap to budget |
|---|---|---|
| Adopted budget | $170.3M | |
| November 2025 forecast | $167.4M | $2.9M short |
| January 2026 forecast | $162.8M | $7.4M short |
| May 2026 forecast | $166.3M | $3.9M short |
| Collected, unaudited | $166.5M | $3.8M short |
The first three gaps are the ones the city printed. Its tables round to one decimal and carry the note "Tables may not foot due to rounding," so a gap can differ from the plain subtraction by $0.1 million.
In January, the city blamed "a significant decline in international travel and tempered growth in both leisure and business travel." By May, the forecast had come back up as more months were paid in. It ended within $0.2 million of what was collected. The budget missed by $3.8 million, about 2.2%.
Now look at what the budget did all year. It kept saying $170.3 million, because that's its job. A budget is the promise you're measured against. The forecast's job is to tell you, as early as it can, how far off that promise you're going to land.
Did the forecast beat the budget?
On most lines, yes, but not every one. Here are San Diego's four biggest taxes, with the last forecast before the year closed:
| Tax | Budget | May forecast | Collected | Closer to the final number |
|---|---|---|---|---|
| Property tax | $844.6M | $847.4M | $841.4M | Budget, by $3.2M against $6.0M |
| Sales tax | $374.5M | $379.2M | $384.9M | Forecast, by $5.7M against $10.4M |
| Hotel tax | $170.3M | $166.3M | $166.5M | Forecast, within $0.2M against $3.8M |
| Franchise fees | $103.6M | $111.4M | $112.1M | Forecast, by $0.7M against $8.5M |
So the forecast won on 3 of 4, and you can see why the fourth went the other way. Property tax is the honest exception. The May forecast assumed growth from higher property values, and the October report says collections came in lower, "primarily due to a lower collection rate," plus $2.8 million more in refunds from assessment appeals and other corrections.
That's a useful lesson for your own numbers. A forecast made later usually knows more, so it's usually closer. It can still be wrong when something late in the year, like a refund or a slow payer, isn't in the data yet.
What the January forecast made the city do
A forecast is only worth its time if somebody acts on it. San Diego's January report shows what that looks like. It found $13.6 million less revenue and $3.2 million more spending than the budget, and it listed the steps the city had taken.
- A memo on November 14, 2025 told departments to cut spending at once.
- Open jobs went through a Request to Fill process that puts mission-critical positions first.
- Discretionary spending and non-essential overtime were suspended.
- Contracts were reviewed to find non-critical services to renegotiate or end.
By May, spending was forecast $15.4 million lower than in January. The report credits several changes, the biggest being a $10.8 million smaller payment into the city's liability fund after one-time insurance money came in for flooding at the Old Central Library. So not all of it was belt-tightening. But the forecast gave the city five months to act, where a budget compared with actuals in October would have given it none.
The May forecast did one more job. The city says it "serves as the basis for the May Revision to the Fiscal Year 2027 Draft Budget." That's the loop in one line. This year's forecast shapes next year's budget.
How to run your own budget and forecast
You don't need a finance department to copy what San Diego did. You need two numbers on each line of your sheet, and a date in your calendar to update one of them.
- Set the budget once, and lock it. Approve it before the year starts and don't edit it when things go wrong. If a real change is approved, keep the original beside the new figure so you can see both.
- Pick a forecast rhythm. San Diego forecast in months 3, 5 and 9. A small business can redo it monthly or quarterly. Pick a schedule and stick to it.
- Say what each forecast stands on. Write how many months of real numbers it uses, the way each city report does. A forecast built on 3 months deserves less trust than one built on 9.
- Show the gap to budget on every line. Put budget, forecast and gap side by side, so a reader sees at once which lines are drifting.
- Write down the reason for each big move. San Diego's year-end report explains every major tax that moved more than $1.0 million from the May forecast. Set your own line, such as 5% or $5,000.
- Name the action. If the forecast says you'll miss, list what you'll change and by when.
Want to know how good your forecasts are? Wait until your year ends, then lay each one beside your final number, the way we did above. Forecasts that keep losing to the budget need rebuilding, with fewer guesses and more of your real monthly numbers.
Five One-Pagers that put a budget beside a forecast
The MakeOnepagers samples below use made-up companies and numbers. Each one shows a fixed plan and a moving estimate on the same sheet.
A building project's forecast at completion
Edit this template
This project budget variance report sets a $1.2M budget beside a forecast at completion of $1,238,000, at week 18 of 26. That's $38,000 over, or 3.2%, with $742,000 spent so far. Electrical work leads the gap at $41K over, after old wiring was found behind the walls. The recommendation asks for $41,000 from the owner's reserve this week, so the walls can close on November 2 and the clinic still opens January 15. Run a forecast like this on any project you manage, because money spent to date tells you little about where the job will finish.
A quarter's report with the full-year forecast on it
Edit this template
For the quarter to September 30, this budget variance report puts $2.41M of spending beside a $2.30M plan, then adds one more line: a full-year forecast of 6% over. Contractors run 22% over and travel 20% under. The quarter itself came in $110k over plan, built up month by month at $20k, $50k and $40k. The recommendation releases $90k from contingency and says the contractor overspend stops in November. Add a full-year line like this to your own quarterly report, so readers see the year as well as the quarter.
A CEO brief that starts from the gap
Edit this template
This budget brief for a CEO opens with a forecast: the 2027 plan spends $3.2M more than the company expects to earn. Five changes save $3,440K against that gap, which leaves $240K to spare and keeps all 46 engineering roles. Each change says who feels it and whether it can be undone. Use this layout when your forecast says the budget won't hold and someone has to choose what to change.
A budget request before the year starts
Edit this template
This budget proposal is the budget at the very start, before any forecast exists. It asks for $1,284,000 for FY2027, up 11.7% on $1,150,000, and sets targets of $7.10 per ticket and a 94% renewal rate. The ask is a single date: approve on November 18, 2026. Once you get it approved, this is the fixed line you measure every forecast against next year.
A monthly snapshot that looks ahead
Edit this template
This team budget snapshot works on a smaller scale. A $50,000 monthly marketing budget shows paid ads at $16,200 against $15,000, then looks forward. It lists $13,500 of payments coming up from November to December, including a $4,800 CRM renewal on November 3. Keep a list like that on your own sheet. It's a forecast in its plainest form, the money you already know is about to leave.
Make your budget and forecast sheet
Open the MakeOnepagers budget that fits your team, then give it a forecast column beside the budget column. Got last year's spreadsheet? Drop its figures into the free AI One-Pager generator and it sets up the sheet for you. When the year is over, compare the result with the plan using our budget vs actual guide. To build the plan itself, start with how to write a budget. Forecasting sales? Read sales forecast vs sales projection to label it right.
Frequently asked questions
Can a forecast be higher than the budget?
Yes. A forecast is an estimate of what will happen, so it can land above or below the plan. In San Diego's May 2026 report, sales tax was forecast at $379.2 million against a $374.5 million budget, and the city collected $384.9 million.
Should you change the budget when the forecast changes?
Usually not. Keep the approved budget fixed so you can measure against it, and let the forecast carry the new estimate. San Diego's budget moved by only $3.7 million in a year when its forecast bottom line swung by $18.5 million. When a real change is approved, show the original and the new figure side by side.
How often should a forecast be updated?
Often enough to act on it. San Diego forecast three times in 12 months, after 3, 5 and 9 months of real numbers. Monthly or quarterly works for most businesses. A business with fast-moving cash can go further and forecast weekly.
What's the difference between budget vs forecast vs actual?
The budget is the plan you approved. The forecast is your current estimate of the final number. The actual is what really happened, known only when the period ends. San Diego budgeted $170.3 million of hotel tax, forecast $166.3 million in May, and collected $166.5 million.
Is a rolling forecast the same as a budget?
No. A rolling forecast keeps adding a new month or quarter at the end, so it always looks the same distance ahead. A budget covers a fixed year and stays put once it's approved.