  • The one thing to act onSummary
  • Workstream statusStatus by Workstream
  • Schedule chartTimeline (weeks)
  • TableBudget ($K)

Sample One-Pager. Company and figures are made up.

Make it yours with your own numbers

Project Status: New Warehouse System
Week 18 of 30 · Owner: Grace Kim · Sample figures
Summary
On budget and one week behind. Barcode scanners arrived late, so testing moved from 2 to 9 November. Go-live on 7 December still holds.
Status by Workstream
Workstream
Owner
Status
This week
Software set-up
Grace K.
On track
All 14 screens configured
Scanners and printers
Ali R.
At risk
Delivered a week late
Data move
Ming T.
On track
2 of 3 trial runs passed
Staff training
Sofia P.
Late
Only 40% booked so far
Timeline (weeks)
Software set-up
Data move
Scanners and printers
Testing
Training
Go-live
weeks
Budget ($K)
ItemBudgetSpentLeft
Software42038040
Hardware1601528
Consultants21011892
Training601248
Total850662188